• 3 minutes e-car sales collapse
  • 6 minutes America Is Exceptional in Its Political Divide
  • 11 minutes Perovskites, a ‘dirt cheap’ alternative to silicon, just got a lot more efficient
  • 1 min GREEN NEW DEAL = BLIZZARD OF LIES
  • 3 hours How Far Have We Really Gotten With Alternative Energy
  • 5 hours If hydrogen is the answer, you're asking the wrong question
  • 4 days Oil Stocks, Market Direction, Bitcoin, Minerals, Gold, Silver - Technical Trading <--- Chris Vermeulen & Gareth Soloway weigh in
  • 5 days The European Union is exceptional in its political divide. Examples are apparent in Hungary, Slovakia, Sweden, Netherlands, Belarus, Ireland, etc.
  • 18 hours Biden's $2 trillion Plan for Insfrastructure and Jobs
  • 4 days "What’s In Store For Europe In 2023?" By the CIA (aka RFE/RL as a ruse to deceive readers)
Gold Prices Soar Past $2,150 After Bullish Rally

Gold Prices Soar Past $2,150 After Bullish Rally

Precious metal prices experienced a…

OPEC Remains Upbeat About Oil Demand

OPEC Remains Upbeat About Oil Demand

OPEC remains optimistic that the…

Leonard Hyman & William Tilles

Leonard Hyman & William Tilles

Leonard S. Hyman is an economist and financial analyst specializing in the energy sector. He headed utility equity research at a major brokerage house and…

More Info

What A Westinghouse Bankruptcy Could Mean For U.S. Utilities

International news services now report that Japan’s Toshiba Corporation (9502.T) is preparing to make a chapter 11 bankruptcy filing for its Westinghouse Electric subsidiary as soon as this Monday, March 27. For most of our readers this news evokes little surprise. This is merely another chapter of a slow moving financial and accounting train wreck involving nuclear design and construction firm Westinghouse and its troubled Japanese parent, Toshiba. But like an old, leaky garbage scow there is much to clean up in its wake.

The two U.S. utilities with the most at risk are Southern Company and SCANA Corp. Westinghouse is presently constructing two unit, AP 1000 nuclear power stations for each utility. These projects are over-budget and behind schedule. It appears that Westinghouse offered both utilities a fixed price contract for these new nuclear plants. Our best guess is that this fixed price construction guarantee has doomed Westinghouse and prevented other potentially willing buyers from stepping in. No one it seems is willing to take on this seemingly open-ended nuclear construction liability.

What does this mean for the two domestic utilities embroiled in this international financial quagmire?

First, we expect that they will complete both nuclear construction projects. The bulk of heavy capital expenditures for both utilities seem to be in the 2017-2019 period.

Second, it is in all interest of all potential litigants to see these plants completed. Westinghouse/Toshiba, for one, would at least get to showcase the AP 1000 design and its successor entity could advocate for additional sales of this reactor design. A working design has value. (What happens in the UK is another matter where Toshiba hoped to build several plants). The utilities, which need new power stations, get large, rate based, non-fossil base load power generating resources for the next 40-60 years.

The worst case scenario for utility investors would be if the utilities had to cancel the projects and take big write offs. But we assign a very low probability to this scenario.

Related: TransCanada Gets Presidential Permit To Build Keystone XL

Perhaps, more likely, a Westinghouse bankruptcy means abrogation of the fixed price contracts signed with Southern and SCANA. News reports this week indicated that both utilities had hired bankruptcy counsel.

As these plants are brought on line, presumably in the 2020-2021 time frame, the matter will go before the state utility commissions of Georgia and South Carolina. Both commissions approved these nuclear projects. It’s just that the plants will cost more than expected.

ADVERTISEMENT

Unfortunately for investors, they will have to live with uncertainty until the regulators make their decisions. There are no clear precedents for the decisions, other than that commissions typically allocate or split unexpected financial burdens like these between shareholders and consumers. And that the amounts at risk won’t be modest given the size of the projects.

By Leonard Hyman and Bill Tilles for Oilprice.com

More Top Reads From Oilprice.com:



Join the discussion | Back to homepage



Leave a comment
  • Paxus Calta on March 29 2017 said:
    The real question in the Westinghouse bankruptcy is how do the unfinished reactors at Summer and Vogtle get completed. The Chinese who already have their own version of the AP 1000 will have no problem completing the reactors at Sanmen and Haiyang which are nearly finished (after 3 year delay).

    Normally, a utility going into chapter 11 would dump it's debt, generally screwing over workers and creditors (as PG&E did). The problem that WH faces with the unfinished US reactors is that no one believes the $6 billion that they are currently over budget is the end of the problems for these plants. Thus if WH files for Chapter 11, gets a favorable debt reorganization by the judge, comes back into business having shifted it's debt to SCANA and Georgia Power (the operating utilities) it will then a couple years after the bankruptcy be facing more billions in debt because they can't build these reactors for the prices that they bid.

    These prices were bid this low to fool utilities and public utility commissions that these reactors were good value. If Westinghouse had not done this trick multiple times in the past the utilities and PUC could be forgiven for falling for it. But basically WH has done this with every one of the last 30 reactors they have built in the US, all of which are over budget all of which were late. Previously WH did not need to go bankrupt, because they refused to sign fixed cost contracts, this way there was no way to land the contracts without this mock insurance.

    https://funologist.org/2017/03/25/the-death-of-westinghouse/
  • Sidney Hale on March 27 2017 said:
    Monday in March 27th, not March 31st.

Leave a comment

EXXON Mobil -0.35
Open57.81 Trading Vol.6.96M Previous Vol.241.7B
BUY 57.15
Sell 57.00
Oilprice - The No. 1 Source for Oil & Energy News