• 4 minutes England Running Out of Water?
  • 7 minutes Trump to Make Allies Pay More to Host US Bases
  • 10 minutes U.S. Shale Output may Start Dropping Next Year
  • 14 minutes Washington Eyes Crackdown On OPEC
  • 2 hours Tidal Power Closer to Commercialisation
  • 1 hour US-backed coup in Venezuela not so smooth
  • 7 hours Why U.S. Growers Are Betting The Farm On Soybeans Amid China Trade War
  • 6 mins Oil-sands recovery by solvents has started on a trial basis; first loads now shipped.
  • 6 hours Read: OPEC THREATENED TO KILL US SHALE
  • 1 day BATTLE ROYALE: Law of "Supply and Demand". vs. OPEC/Saudi Oil Cartel
  • 14 hours Fisker Announces 'Mass Market' Electric SUV
  • 15 mins New Rebate For EVs in Canada
  • 33 mins Solar to Become World's Largest Power Source by 2050
  • 3 hours Biomass, Ethanol No Longer Green
  • 2 hours Malaysia Oil & Gas Updates
  • 1 day Trump Tariffs On China Working
Allen Gilmer

Allen Gilmer

Allen writes the popular energy news blog Open Choke

More Info

Trending Discussions

The BP Blowout - Part 2

Below is the TransOcean rig data on the wellbore from two hours out until blowout.
This from what was filed with the US government investigators. So what does it say?

It says that the well wasn't drilling (no ROP (or Rate of Penetration), no Torque or RPM data which measures how smoothly and quickly the drill string turns). 

It shows that the fluid had a constant mudweight of 16 lbs per gallon, which is probably in error. The mudweight was reported to be 14 lbs per gallon, and the replacement of mud with seawater is reported to have started at 8:00 p.m. (20:00).

TransOcean Rig Data

You see an immediate increase in Flow In (fluids flowing up inside the casing) as well as Stand Pipe Pressure, with a dramatic increase in Pit Volume Change beginning at 8:10 (this means that what is coming out of the hole has more volume than what was put in the hole, and a true indicator that the reservoir was NOT isolated by the cement job), along with a gas kick within the mud (coming out between casing and hole) beginning at 8:16.  All of this points to the fact that the reservoir was not controlled by the cement job in place. Presumably, they must have felt they could control it with the BOP. 

It looked like they tried to control it and probably felt like they had a handle on it by about 9:10, as the pit volumes dropped, perhaps indicating they began mudding up to stop flow, but they were still circulating it looks like.  

It took a secondary kick from around 9:14 to around 9:30 and settled down. 
Then, at 9:47, the well took a dramatic kick, and blew out at 9:50.

By. Allen Gilmer