• 3 minutes e-car sales collapse
  • 6 minutes America Is Exceptional in Its Political Divide
  • 11 minutes Perovskites, a ‘dirt cheap’ alternative to silicon, just got a lot more efficient
  • 21 mins GREEN NEW DEAL = BLIZZARD OF LIES
  • 22 hours Could Someone Give Me Insights on the Future of Renewable Energy?
  • 24 hours How Far Have We Really Gotten With Alternative Energy
  • 5 days e-truck insanity
  • 3 days An interesting statistic about bitumens?
  • 8 days "What’s In Store For Europe In 2023?" By the CIA (aka RFE/RL as a ruse to deceive readers)
  • 7 days Oil Stocks, Market Direction, Bitcoin, Minerals, Gold, Silver - Technical Trading <--- Chris Vermeulen & Gareth Soloway weigh in
LNG Bunkering Sales Off to a Strong Start in 2024

LNG Bunkering Sales Off to a Strong Start in 2024

LNG maintains its dominance as…

U.S. Sees New Egyptian Gas Fields As Key To Its New Middle Eastern Strategy

U.S. Sees New Egyptian Gas Fields As Key To Its New Middle Eastern Strategy

Besides its important geo-strategic location,…

Lower Natural Gas Prices Squeeze Big Oil's Profits in Q1 2024

Lower Natural Gas Prices Squeeze Big Oil's Profits in Q1 2024

U.S. supermajors ExxonMobil and Chevron,…

Keith Schaefer

Keith Schaefer

Keith is the publisher of the Oil & Gas Investments Bulletin – an investment newsletter that looks at opportunities within the Canadian small cap oil…

More Info

Premium Content

Canada's LNG Dream – Racing Ahead…at a Snail's Pace

Canada's LNG Dream – Racing Ahead…at a Snail's Pace

According to a new Financial Post story, the number of countries exporting Liquefied Natural Gas (LNG) is expected to double – to 50 – by the year 2020.

So what's holding up export proposals for Canada’s west coast?

These 3 factors, mainly...??

1. Permits

2. Taxes

3. Offtake deals??

Today's story focuses on permitting—but you'll first want to recall that the first LNG proposal that will export BC and Alberta gas—the Douglas Channel project with Golar (GLNG-NASD) – is so small at 0.2 bcf/d that it doesn’t need all this permitting.??Very small projects like that don't need the big permits, just some small ones.  

This article is about the big LNG proposals, like Shell and Chevron and Petronas.??So with that in mind…what is the permitting process for a proposed liquefied natural gas export facility? What are the biggest challenges???

Step 1: The National Energy Board (NEB)??

The first hurdle – an export license from the federal National Energy Board – tests whether the project is in Canada's economic best interests.??LNG proponents apply to the NEB to ship certain volumes of LNG annually for a set number of years. To grant an export license the board must find that the proposal is in the public interest and that the energy commodity to be exported is surplus to Canada's energy needs.??

Here the "best interest" question is only economic – the NEB is not charged with considering environmental impacts. Since the province – nay, the continent – is overflowing with natural gas and its export should generate all kinds of jobs and tax revenues, it's little surprise that the board has approved every single LNG export license so far.??Three projects – Douglas Channel, Kitimat LNG, and LNG Canada – have already obtained NEB authorization. Three other applications are under review.

Related article: Canada's Offshore Versus Shale Gas

Step 2: Environmental Approval??

The environmental assessment (EA) process is the longest and most complicated permitting step – and it carries the least certainty. To earn a green light projects have to meet the goals of environmental, economic, and social sustainability.?

To that end, the EA process examines each project for anything that could be environmentally, economically or socially bad, and what heritage and health effects that may occur over the project's entire life cycle.??That means talking to A LOT of people...??

1.  Consulting with First Nations,

2.  Completing in-depth technical studies on potential significant adverse effects,??

3.  Designing strategies to prevent or reduce those adverse effects, and then putting all the input and findings into a huge report that carries a recommendation to the Minister of the Environment and the Minister of Natural Gas on whether the project should be allowed – or not.??

There’s a “Pre-Application Phase," where the Environmental Assessment Office (EAO) decides if the project does indeed need EA approval and, if it does, how the approval process should work.??There is a lot of back-and-forth between the government and the company submitting the proposal—more technical data, engineering, proof of consultation, etc.??

Once the full “Application Review Phase” starts, the EAO has 180 days to complete its review. That period includes a 45- to 60-day public comment period that includes open houses.??The EAO writes up a draft report that it shares with the proponent, the working group, and with First Nations, adding in any input. The final report includes a recommendation from the executive director of the EAO on whether an EA certificate should be issued and a draft EA certificate.?

The draft certificate lists commitments the proponent made during the EA process to address concerns. It is not uncommon for an EA certificate to have more than 100 commitments – which are all legally binding if the certificate is signed.??It then goes to the government and the ministers have 45 days to make a decision. They can issue the EA certificate with the commitments listed, refuse to issue a certificate, or require further study.??Things have gotten easier on the EA front in recent years. In its recent budget the federal government handed almost all control of the EA process for energy projects to the provinces—before, they both did one. Sigh.??

Related article: Terrorism: The Latest Salvo on LNG Exports

It's a good move, but pipelines are still considered separate projects from the LNG facilities themselves, so that’s another entire EA approval process.??

The First Nations Issue

First Nations support is vital. Earning support for a LNG facility might not be too hard. Pipelines are a different story – and every facility needs one.??Anyone who wants to build a pipeline across northern BC likely has to consult with at least half a dozen First Nations, each with a different set of expectations and demands.??If you can find common ground, deals between project proponents and affected First Nations take the form of Impacts and Benefit Agreements.

There are lots of examples – but the biggest challenge is that there still is no clear definition of what constitutes sufficient consultation, mitigation, and benefits. A poorly defined end game, to say the least. Sometimes the road is smoother. The Haisla First Nation that occupies territory near Kitimat and at the head of the Douglas Channel is involved in three LNG proposals.?

ADVERTISEMENT

The Haisla are viewing this as an opportunity: they believe the deals that will flow from these LNG projects could give their people the ability to simply buy the lands they believe are theirs, without a treaty (and negotiations have been going on for years, if not decades).??

More Permits

After this, work cannot start on the liquefaction plant until the project earns a facility permit from the BC Oil and Gas Commission. Then there are five different Acts that a facility must comply with—after the big EA approval has been won.??The process isn't any more arduous than in other places, though it is a new ballgame with rules being made up on the fly. But BC offers advantages to would-be LNG exporters over other locales.

1.     The transport route from BC to Asia is only 9-10 days vs. 20-plus days for LNG ships out of the Gulf of Mexico.??

2.     LNG is 30% more efficient in the cold weather of northwest BC vs. tropical areas.??

3.     Canadian gas fields have liquids like ethane and butane, which add value by increasing the fuel's energy density. A lot of US LNG has to add this in.??That's great for would-be exporters...but on the flip side, the flood of interest raises some big picture questions for British Columbians and for the regulators charged with developing this brand new industry.??How many natural gas pipelines should be built across northern BC??

Is a fleet of independent facilities the best approach, or should proponents be required to rationalize some of their infrastructure?

How should the operations be powered? How much should they be taxed???The next two years we'll see those questions answered.

By. Keith Schaefer, Editor, the Oil & Gas Investments Bulletin


Download The Free Oilprice App Today

Back to homepage





Leave a comment

Leave a comment




EXXON Mobil -0.35
Open57.81 Trading Vol.6.96M Previous Vol.241.7B
BUY 57.15
Sell 57.00
Oilprice - The No. 1 Source for Oil & Energy News